Heerema Marine Contractors has completed the installation of 64 monopile foundations for the He Dreiht Offshore Windfarm, Germany’s largest offshore wind farm.
Heerema Marine Contractors (HMC) has secured contracts from MFW Baltyk II and MFW Baltyk III, joint ventures co-owned by Equinor and Polenergia, for its heavy-lift…
Heerema Marine Contractors are close to putting new monopile lifting tools into service, as it has taken delivery of new equipment after two years of…
Heerema’s installation of the world’s first unmanned High Voltage Direct Current (HVDC) offshore substation means the world’s largest offshore wind farm, Dogger Bank, has ticked…
The installation of Arcadis Ost 1 offshore wind turbines has come to a close for now as Heerema Marine Contractors completed the installation of 24…
Earlier this month, Heerema Marine Contractors’ semi-submersible crane vessel Thialf installed the 4,200 – metric tonne topside of the Baltic Eagle offshore wind farm, for…
Each week, Project Cargo Journal will be sharing one photograph, showcasing industry activity. This week’s photograph of its heavy-lift behemoth Sleipnir is courtesy of Heerema…
Green energy company, Parkwind turned to Heerema Marine Contractors for a premiere in the wind turbine installation on commercial scale. The two companies have come…
Heerema Marine Contractors’ crane vessel Thialf has made the first crossing of the Storebaelt Bridge, known as the ‘gate to the Baltic Sea’. It is…
The last of the decommissioned Kinsale platform structures have finally been moored at the Hoondert Services & Decommissioning (HSD) location in Vlissingen. The feet comes…
The semi-submersible crane vessel Sleipnir will soon install the manifold and gantry modules on Equinor’s Johan Castberg, a floating production storage and offloading (FPSO) vessel.
Heerema Marine Contractors has started the installation of the gravity base structure foundations at the Fécamp offshore wind project in Normandy, France. The project has…
Heerema Marine Contractors has secured a decommissioning contract by Woodside Energy that includes the integrated engineering, preparation, removal, and transport of the Nganhurra riser turret…
The Norwegian company Aibel has contracted Heerema for the transport and installation of two offshore converter stations (OCS) for the Hornsea 3 offshore wind farm,…
Heerema Marine Contractors and AF Offshore Decom operating together under the name ‘HAF Consortium,’ have successfully removed the topsides of Fairfield Energy’s Dunlin Alpha. The…
For the first time in the heavy lift industry, Lankhorst Ropes is supplying Heerema Marine Contractors with LankoForce HL slings manufactured with Dyneema SK78 fibre…
Heerema Marine Contractors successfully performed the hooking down and removal of the decommissioned PSE Kinsale Energy Bravo platform, in the Kinsale Area gas fields. Following…
Philippe Barril will be stepping down as Chief Transition Officer (CTO) for SBM, and replacing Koos-Jan Brouwershaven as Chief Executive Officer (CEO) of Heerema Marine…
Heerema CEO, Koos-Jan van Brouwershaven has unveiled his decision to leave the helm of the company effective May 31, 2022. Van Brouwershaven was the CEO of…
Heerema Marine Contractors has been contracted by EnBW to transport and install monopiles and transition pieces at the He Dreiht offshore wind farm.