German contractor uses new lifting system for Berlin bridge section removal

German contractor uses new lifting system for Berlin bridge section removal

Photo Autokrane Schares GmbH.

German heavy lifting specialist Autokrane Schares has completed the removal of a bridge section in Berlin using a new lifting system for the first time. The project involved removing a 60-meter-long section of the Marggraff Bridge, weighing 1,500 tonnes, over the Britzer Verbindungs Canal.

The presence of overhead power lines and limited space at the busy intersection necessitated a lifting solution that minimised disruption. Autokrane Schares put its recently acquired Enerpac JS-250 jack-up system to good use.

The compact design of the JS-250 allowed for its installation on the narrow canal towpath. The bridge deck was sectioned to create space for positioning the jack-up tower bases and beams. Additional jack-up tower components were then added from a pontoon positioned on the canal.

Synchronized lifting of the bridge section was achieved using interconnected pumps, ensuring stability throughout the operation.

The 1,500-tonne bridge deck was removed in three stages over two weeks. For each stage, the JS-250 raised the bridge section 3 meters, allowing it to be transferred onto pontoons positioned beneath. The bridge section was then floated to a nearby site for dismantling.

Space restrictions at the site made this a very challenging project,” said Max Boere, Team Leader SPMT, Autokrane Schares. β€œThe compactness and ease of set-up, together with accurate synchronised lifting, made the Enerpac JS-250 a perfect fit for this project.”

You just read one of our premium articles free of charge

Want full access? Take advantage of our exclusive offer

See the offer

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

German contractor uses new lifting system for Berlin bridge section removal

German contractor uses new lifting system for Berlin bridge section removal

German contractor uses new lifting system for Berlin bridge section removal
Photo Autokrane Schares GmbH.

German heavy lifting specialist Autokrane Schares has completed the removal of a bridge section in Berlin using a new lifting system for the first time. The project involved removing a 60-meter-long section of the Marggraff Bridge, weighing 1,500 tonnes, over the Britzer Verbindungs Canal.

The presence of overhead power lines and limited space at the busy intersection necessitated a lifting solution that minimised disruption. Autokrane Schares put its recently acquired Enerpac JS-250 jack-up system to good use.

The compact design of the JS-250 allowed for its installation on the narrow canal towpath. The bridge deck was sectioned to create space for positioning the jack-up tower bases and beams. Additional jack-up tower components were then added from a pontoon positioned on the canal.

Synchronized lifting of the bridge section was achieved using interconnected pumps, ensuring stability throughout the operation.

The 1,500-tonne bridge deck was removed in three stages over two weeks. For each stage, the JS-250 raised the bridge section 3 meters, allowing it to be transferred onto pontoons positioned beneath. The bridge section was then floated to a nearby site for dismantling.

Space restrictions at the site made this a very challenging project,” said Max Boere, Team Leader SPMT, Autokrane Schares. β€œThe compactness and ease of set-up, together with accurate synchronised lifting, made the Enerpac JS-250 a perfect fit for this project.”

You just read one of our premium articles free of charge

Want full access? Take advantage of our exclusive offer

See the offer

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.