First heavy lift in the bag at Brevik CCS

First heavy lift in the bag at Brevik CCS

Photo: Brevik CCS

A 50 metres tall absorber unit weighing approximately 202 tons has been set in its place at the Heidelberg Materials pioneer project in Brevik. The company noted the highly complex lift was a major milestone. 

“Yesterday we installed the first part of the absorber in the carbon capture plant. The absorber is in many ways the heart of the carbon capture process because it is where the flue gases are separated,” said Tor Gautestad, Operational Manager for Brevik CCS.

The complete absorber unit installation on site will take some 10 to 14 days

Read also: Can CCS projects be developed on supply chain crumbs left behind offshore wind?

Gautstad said that the ongoing operation is symbolic and important. “Now everyone can see with their own eyes what we’ve been working so hard on. This lift has been planned for many months and years, and it was a very complex task where many partners were involved,” he said.

“The leeway was only down to 1 mm in the end, which isn’t much when you’re moving something of this size. Excellent engineering and collaboration, and as always – safety was key,” said Gautestad.

Second heavy lift to follow shortly

Heavy lifting will continue immediately the week after when the absorber stack will be mounted on top of the absorber. The absorber will then be over 100 meters tall, a height in comparison higher than the Big Ben in London. To achieve this, the crane, which is close to 75 meters today, will be further elevated to a height of 115 meters.

“I’m looking forward to next week’s lift as well, hopefully, it will be another spectacular lift and really showcase to the world that we’ve moved another step towards finalisation of the world’s first full-size carbon capture unit at a cement plant,” Gautestad said.

Read also: Carbon capture equipment shipped from Belgium to Norway

Care to learn more about Carbon Capture and Storage? Then join us at the upcoming Project Cargo Summit to be held on September 6-7 in Bremen, Germany. Have you secured your seat yet? There are less than two weeks to go, register here!

You just read one of our premium articles free of charge

Register now to keep reading premium articles.

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.

First heavy lift in the bag at Brevik CCS | Project Cargo Journal

First heavy lift in the bag at Brevik CCS

First heavy lift in the bag at Brevik CCS
Photo: Brevik CCS

A 50 metres tall absorber unit weighing approximately 202 tons has been set in its place at the Heidelberg Materials pioneer project in Brevik. The company noted the highly complex lift was a major milestone. 

“Yesterday we installed the first part of the absorber in the carbon capture plant. The absorber is in many ways the heart of the carbon capture process because it is where the flue gases are separated,” said Tor Gautestad, Operational Manager for Brevik CCS.

The complete absorber unit installation on site will take some 10 to 14 days

Read also: Can CCS projects be developed on supply chain crumbs left behind offshore wind?

Gautstad said that the ongoing operation is symbolic and important. “Now everyone can see with their own eyes what we’ve been working so hard on. This lift has been planned for many months and years, and it was a very complex task where many partners were involved,” he said.

“The leeway was only down to 1 mm in the end, which isn’t much when you’re moving something of this size. Excellent engineering and collaboration, and as always – safety was key,” said Gautestad.

Second heavy lift to follow shortly

Heavy lifting will continue immediately the week after when the absorber stack will be mounted on top of the absorber. The absorber will then be over 100 meters tall, a height in comparison higher than the Big Ben in London. To achieve this, the crane, which is close to 75 meters today, will be further elevated to a height of 115 meters.

“I’m looking forward to next week’s lift as well, hopefully, it will be another spectacular lift and really showcase to the world that we’ve moved another step towards finalisation of the world’s first full-size carbon capture unit at a cement plant,” Gautestad said.

Read also: Carbon capture equipment shipped from Belgium to Norway

Care to learn more about Carbon Capture and Storage? Then join us at the upcoming Project Cargo Summit to be held on September 6-7 in Bremen, Germany. Have you secured your seat yet? There are less than two weeks to go, register here!

You just read one of our premium articles free of charge

Want full access? Take advantage of our exclusive offer

See the offer

Author: Adnan Bajic

Add your comment

characters remaining.

Log in through one of the following social media partners to comment.